Village of Fisher Public Works Committee met Sept. 29

Village of Fisher Public Works Committee met Sept. 29.

Here are the minutes provided by the committee:

Meeting called to order at 6:05. 

Committee members present were: Brock Deer, Roger Ponton, and Joe Brown 

Also attending: Brenda Cook (Village Public Works Employee) Brandon Chandler (Chandler Concrete), and Will Grey (Donohue and Associates) 

No comments from the public/press 

Phase 1 of the Drainage project is the downtown area. We need to determine what type of bottom the catch basin has. Brandon Chandler and Jay Bullock will work on this. They may use the Jet Machine to clean out the bottom while they are checking. 

Phase 2 of the Drainage project is the Fairfield area. A manhole needs to be added via change order. There was discussion on how the change order and invoices need to be submitted to Donohue. Brandon Chandler is submitting the invoices next week and Will Grey from Donohue will review them for approval. Will Grey will let the village office know what to put on the agenda for payment. 

During the project it was discovered that was damage caused by Frontier when installing fiber line through the village clay drainage tile. A field investigation was preformed last week and Donohue is working with Frontier and the village to resolve and fix the problem. 

Meeting was adjourned at 6:36 pm. 

https://fisher.il.us/file/400/Septmeber%2029%202022%20Public%20Works%20Committee%20Meeting%20Minutes.pdf

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS